          the form envisaged in the October 2016   The question now becomes what will be   7.  Support  the  development  of  gas
          Preliminary  Information  Memorandum   required of these projects in order to for   infrastructure  by  converting  all
          and the Information Memorandum.   the  Minister  to  grant  the  deviation  and   diesel-fired  power  plants  (peakers)
          Hydro                             the timing implications of this process.  to gas;
          In  support  of  regional  integration  and   Ministerial Determinations  8.  Immediately commence the nuclear
          energy trading, South Africa has entered                                 build programme up to 2,500MW in
          into  a  Treaty  for  the  development  of,                              case the Grand Inga project does not
          and the purchase of 2,500MW of hydro-                                    materialise and because it is a “no-
          electric  power  from,  the  Grand  Inga   IRP  2019  confirms  that     regret option” - we understand from
          Project  in  the  Democratic  Republic  of                               the press at the time of publication
          Congo  (DRC),  with  some  of  the  power   the  existing  Ministerial   that  the  Department  of  Mineral
          intended for transmission to South Africa   Determinations  in  issue  will   Resources and Energy may publish an
          across  DRC,  Zambia,  Zimbabwe  and   be looked at and revised in       erratum to IRP 2019 so that this Policy
          Botswana,  in  part  in  pursuit  of  regional   line with the latest approved   Position  reads  that  government  will
          integration in SADC.                IRP. This will be done in            commence preparations for a nuclear
                                                                                   build  programme  to  the  extent  of
          Distributed Generation              concurrence with NERSA as            2,500MW  at  a  pace  and  scale  that
          IRP   2019   provides   for   uncapped     required by law.              the country can afford because it is
          procurement  of  Distributed  Generation                                 a no-regret option in the long term;
          up to and including 2022, and thereafter,   Nine  Policy  Positions  to  and
          procurement  would  be  capped  at   prevent  load  shedding  and    9.  South  Africa  must  support  strategic
          500MW per year up to 2030. Distributed   extensive diesel consumption.   power  projects  in  neighbouring
          Generation is defined in IRP 2019 to mean                                countries   that   enable   the
          “small-scale  technologies  to  produce                                  development   of   cross-border
          electricity  close  to  the  end  users  of                              transmission infrastructure.
          power”.    IRP  2019  suggests  elsewhere   IRP 2019 sets out nine policy supply and
          that  distributed  generation  projects   demand  side  interventions  in  the  short
          include projects between 1 and 10 MW.   term to minimise the risk of load shedding
          This  is  an  opportunity  for  small-scale   (power  black-outs)  and/or  extensive  use
          generators, including those from biomass,   of diesel peaking plants:
          biogas,  landfill  gas  and  co-generation,
          but  IRP  2019  appears  to  exclude  mines   1.  Immediate  initiation  of  a  medium-
          and  commercial  and  industrial  entities   term power purchase programme to
          that  are  seeking  to  develop  generation   create reserve capacity;
          capacity  in  excess  of  10MW.    IRP  2019   2.  Immediate   commencement   of
          provides  that  embedded  generation   technical and regulatory work for the
          installations  in  excess  of  10MW  would   20-year  extension  of  the  life  of  the   Jason van der Poel
          require  a  “Ministerial  deviation  in  line   Koeberg nuclear power plant;
          with the Electricity Regulation Act”.
                                            3.  Support Eskom financially and legally
                                                to  comply  with  minimum  emissions
                                                standards;
           The  developers  of  projects
           above 10 MW are required         4.  Convene  a  team  to  put  together  a
           to apply for and obtain an           just  transition  plan  within  a  year  in
                                                consultation with all social partners;
           exemption from the Minister
           of Energy from the obligation    5.  Retain the current annual build limits
                                                on  renewables  (wind  and  PV)  until
           to comply with the IRP2019           the  report  on  the  just  transition  is
           in terms of section 10(2)(g)         released;                                Alexandra Felekis
           of Electricity Regulation Act,   6.  South Africa should not sterilise the
           before an application for a          development  of  its  coal  resources
           generation licence can be            for  purposes  of  power  generation,
           considered  by  the  National        but  instead  plan  for  energy  and  an
           Energy  Regulator  of  South         environment  that  supports  a  just
                      Africa.                   transition;